构皮滩升船机承船厢现场拼焊施工设计方案

  

  1. 杭州国电机械设计研究院有限公司,杭州〓310030
  • 出版日期:2020-01-25 发布日期:2020-03-20

Design of onsite assembly and welding for Goupitan ship lift chamber

  1. Hangzhou State Machinery Research and Design Institute Company Limited, Hangzhou 310030, China
  • Online:2020-01-25 Published:2020-03-20

摘要: 承船厢现场拼焊是升船机工程施工中的难点工作,主要受场地局限性、施工条件差、工期要求紧等因素制约。介绍了一种承船厢结构拼焊施工设计方案,从承船厢结构分块、吊装转运就位、焊接流程设置等方面进行论述,并从技术特点、工期及经济性、安全、质量4个方面进行效果分析。工程实践表明,该设计方案能够确保施工质量,节约工期,提高工作效率,保证施工安全。

关键词: 升船机, 承船厢结构, 分块, 吊装, 拼焊, 构皮滩, 通航建筑物

Abstract: The onsite assembly and welding for ship lift chamber is the key in the construction of ship lift.It is mainly restricted by the site limitation, poor construction conditions, tight construction period and other factors. It introduces a design of onsite assembly and welding for ship lift chamber including the modularized structure, hoisting in position, and setting of welding process. And it analyzes the design including technical characteristics, construction period and economy, safety and quality. The engineering practice indicates that the design can effectively ensure the construction quality, save the construction period, improve the work efficiency and guarantee the construction safety.

Key words: ship lift, structure of the ship lift chamber, modularization, hoisting, assembly and welding, Goupitan;navigation buildings