华电技术 ›› 2020, Vol. 42 ›› Issue (6): 47-51.

• 燃气发电 • 上一篇    下一篇

燃气-蒸汽联合循环机组余热锅炉热效率计算模型对比分析

  

  1. 1.河南能信热电有限公司,河南许昌〓4610002.中国大唐集团科学技术研究院有限公司华中电力试验研究院,郑州〓4500003.国家电投集团郑州燃气发电有限公司,郑州〓450001

  • 出版日期:2020-06-25 发布日期:2020-06-23

Comparative analysis of calculation models for thermal efficiencies of waste heat boilers in gassteam combined cycle units

  1. 1.Henan Nengxin Thermal Power Company Limited, Xuchang 461000, China2.China Datang Corporation Science and Technology Research Institute Company Limited, Zhengzhou 450000, China3.State Power Investment Group Henan Gas Power Generation Company Limited, Zhengzhou 450001, China

  • Online:2020-06-25 Published:2020-06-23

摘要:

为分析电厂运行的经济性,对某电厂燃气-蒸汽联合循环机组进行了余热锅炉性能试验,利用现场试验数据采取正、反平衡2种数学模型分别计算余热锅炉热效率。在假设系统存在不明泄漏的极端情况下,研究了采用2种模型计算的余热锅炉热效率变化趋势。计算结果表明:额定工况下反平衡余热锅炉热效率为85.69%~85.92%,正平衡余热锅炉热效率为84.50%~85.31%;考虑系统不明泄漏修正的余热锅炉热效率为85.30%~85.94%。反平衡计算模型直接反映出锅炉的换热性能,正平衡计算模型则反映出机组整体热力循环系统的真实情况,2种方法均可为同类机组余热锅炉设备在不同工况下的考核提供参考借鉴。

关键词:

font-size: 10.5pt, mso-spacerun: 'yes', mso-font-kerning: 1.0000pt">余热锅炉, 正平衡, 反平衡, 热效率, 系统不明泄漏

Abstract:

To analyze the economy of power plantsperformance test for a waste heat boiler in a gassteam combined cycle unit was made, and the field test data were taken to calculate the thermal efficiency of the waste heat boiler within positive and counter balance mathematical models.In the extreme situations with unknown leakage in the system, variation trends of the efficiency calculated in two models were studied. The study results showed that the counterbalance waste heat boiler thermal efficiency ranged from  85.69% to 85.92% under the rated conditions, and the efficiency calculated by positive balance ranged from 84.50% to 85.31%.Considering unknown leakage correction,the thermal efficiency of the waste heat boiler ranged from 85.30% to 85.94%. The counterbalance calculation model directly reflects the heat transfer performance of the  boiler. The positive balance calculation model reflects the actual situation of the overall thermal cycle system. These two methods can provide reference forwaste heat boilers  of the same type  under different assessment conditions.