华电技术 ›› 2014, Vol. 36 ›› Issue (9): 8-10.
• 专题综述 • 上一篇 下一篇
出版日期:
Published:
摘要: 摘要:华润彭城2×1000MW机组塔式锅炉工程的安装具有较高的难度,尤其是炉内“三器”受条件限制是安装中的难点。从安装技术的角度出发,设计了一套提升系统,解决了炉内“三器”吊装的技术难题,取得了较好的经济效益和社会效益。
关键词: 关键词:塔式锅炉, 省煤器, 再热器, 过热器, 吊装方案 , 提升系统
Abstract: Abstract:There are larger difficulties in installation of tower type boiler of 2×1000MW unit in Pengcheng Power Plant. Especially, the installation of the “three devices” inside the boiler is difficult point in the boiler installation due to condition restrictions. Starting from the angle of installation technology, a hoisting system was designed, and the technical difficulty in lifting of the “three devices” inside boiler was solved. Better economic benefit and social effect were obtained.
Key words: Keywords:towertype boiler, economizer, reheater, superheater, lifting scheme, hoisting system
吴德胜. 1000MW机组塔式锅炉炉内“三器”专项吊装方案设计[J]. 华电技术, 2014, 36(9): 8-10.
WU Desheng. Design of special lifting scheme of “three devices” inside towertype boiler of 1000MW unit[J]. Huadian Technology, 2014, 36(9): 8-10.
/ 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: https://www.hdpower.net/CN/
https://www.hdpower.net/CN/Y2014/V36/I9/8