华电技术 ›› 2010, Vol. 32 ›› Issue (6): 9-11.

• 专题综述 • 上一篇    下一篇

超临界机组双背压凝汽器抽气系统改造

朱宝森,刘彬,刘尊平,孙光玉   

  1. 华电潍坊发电有限公司,山东潍坊261204
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2010-06-25

Reformation of air extraction system of twopressure condenser in a supercritical unit

ZHU Baosen, LIU Bin, LIU Zunping, SUN Guangyu   

  1. Huadian Weifang Power Generation Corporation Limited, Weifang 261204, China
  • Received:1900-01-01 Revised:1900-01-01 Published:2010-06-25

摘要: 由于高、低背压凝汽器抽空气管路采用串联布置方式,导致高背压凝汽器抽空气排挤低背压抽气,致使低压凝汽器抽空气不能达到设计要求,造成真空值和高、低背压凝汽器背压差值偏低,降低了系统经济性。采取了相应措施,对双背压凝汽器抽气系统进行了改造,经济效益明显。

关键词: 双背压凝汽器, 抽气系统, 端差, 真空, 改造方案

Abstract: The air extraction tubes of highpressure condenser and lowpressure condenser in a unit were arranged in series mode, and this caused the extracted air of highpressure condenser to push aside the extracted air of lowpressure condenser. The air extraction of lowpressure condenser was not reached to the designed requirement; the vacuity of the lowpressure condenser was lower, and the difference between highpressure condenser and lowpressure condenser was also lower. Then the system economical efficiency was decreased. The air extraction system of twopressure condenser had been reformed by adopting some relevant measures, and obvious economical benefit was obtained. 

Key words: two-pressure condenser, air extraction system, pressure difference of terminals, vacuum, reformation scheme