摘要:

介绍了三峡左岸电站ALSTOM机组定子的主要技术参数,提出了定子整体耐压及纯水系统试验的项目及试验标准,拟订了试验顺序及不同试验的具体实施方案,指出了安全注

意事项。

关键词: 定子绕组, 电气试验, 纯水系统, 试验方案, 安全事项

Abstract:

The main technical parameters of stator of the ALSTOMmade unit installed in the Three Gorges Left Bank Hydropower Station were introduced. The

test items and test standards of the stator whole withstanding voltage test and the cooling water system test were put forward; the test sequence and the

concrete implementation plans of different tests were drawn up; and some security matters were pointed out.

Key words: stator winding, electrical test, cooling water system, testing program, security matters