输煤系统在电厂突发事故中的应急处置方案

  

  1. (内蒙古大唐国际托克托发电有限责任公司,内蒙古托克托〓010206)
  • 出版日期:2013-11-25 发布日期:2013-12-30

Emergency disposal scheme of coal handling system of power plant during sudden accident

  1. (Inner Mongolia Datang International Togtoh Power Generation Company Limited, Togtoh 010206, China)
  • Online:2013-11-25 Published:2013-12-30

摘要: 摘要:因华北地区普降大雪,内蒙古大唐国际托克托发电有限责任公司3条500kV输电线路相继跳闸,4台机组被迫紧急停运。输煤系统专业人员启动应急处置预案,根据电厂突发事故的实际情况,制订了事故应急处置方案,全力保障输煤系统设备安全、稳定运行。

关键词: 关键词:跳闸, 应急预案, 输煤系统

Abstract: Abstract:Due to heavy snowfall in wide area of North China, three output transmission lines of Togtoh Power Generation Company Limited tripped successively, four power units were compelled to shut down urgently. According to the actual situation of sudden accident of the power plant, the professionals of coal handling system formulated an accident emergency proposal scheme and tried their best to ensure the equipments of coal handling system to operate safely and stably.

Key words: Key words:trip, emergency plan, coal handling system