Analysis on reasons of lower efficiency of highpressure cylinder of domestic importedtype 300MW steam turbine

WU Qiang, HUA Yudong   

  1. Shanghai Fengxian Gas Turbine Power Generation Company Limited, Shanghai 201403, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2012-11-10 Published:2012-11-10

Abstract: Combining with the practical operation of the 300MW unit of a coalfired power plant, the reasons of lower efficiency of highpressure cylinder in domestic importedtype 300MW steam turbine and typical problems influencing on the unit efficiency were analyzed. A targeted technical improvement scheme was proposed. After the implementation of the improvement scheme, the favorable economic benefit and social effect were obtained.

Key words: steam turbine, high-pressure cylinder, unit efficiency, reason analysis, technical improvement scheme