滨海核电厂取、排水口平面布置工程实例分析

周金全   

  1. 中国大唐集团科技工程有限公司,北京100097
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2011-02-25 发布日期:2011-02-25

Analysis on engineering project of water intake and outlet layout for coastal nuclear power plant

ZHOU Jinquan   

  1. China Datang Technologies and Engineering Corporation Limited, Beijing 100097, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2011-02-25 Published:2011-02-25

摘要: 滨海核电厂取、排水工程设计要考虑海岸稳定、海床泥沙冲淤变化和厂址海域的潮位、波浪、泥沙、海生物等方面的影响。通过工程实例分析,提出了水工布置、结构形式和散热能力之间的优化方案以及取、排水工程设计中的要点。最后指出,滨海核电厂取、排水工程必须进行多方案的技术经济比较论证、水工数模计算及物模试验后,才能确定工程方案。

关键词: 滨海核电厂, 海洋水文, 取, 排水口, 优化方案

Abstract: In the design of water intake and drainage engineering for coastal nuclear power plants, the influence of multiple aspects, such as the coast stability, the variation of sediment flushing on the seabed, the tide level, the wave, the sediment and the sea creatures in the sea area near the plant, must be considered. Through the engineering project analysis, the optimized scheme between the hydraulic engineering allocation, the structure and the heat dissipation capacity was put forward, and the key points in design of the water intake and drainage project were given. It was pointed out finally that for the water intake and drainage project of coastal nuclear power plant, the engineering scheme must be determined on the base of the technical and economical comparison and argumentation of several schemes, the hydraulic numerical simulation calculation and the physical model experiment. 

Key words: coastal nuclear power plant, marine hydrology, water intake and outlet, optimized scheme