摘要: 摘要:针对托电公司500kV出线部分线路跳闸的事故,根据托电公司及呼热公司特定的厂用电接线方式,提出了托电公司厂用电全失后由呼热公司带托电公司厂用电的操作步骤及注意事项,以保障机组安全、稳定运行。
关键词: 关键词:厂用电失去, 供电中断, 辅助蒸汽, 切换
Abstract: Abstract:Aiming at the tripout accident of partial 500kV output transmission lines of Togtoh Power Generation Company Limited, based on the special connection mode of auxiliary power systems of Togtoh Power Generation Company Limited and Hohhot Thermal Power Company Limited, it was proposed that after the auxiliary power system of Togtoh Power Generation Company Limited is all failure, the Hohhot Thermal Power Company Limited will appointed to provide the auxiliary power of Togtoh Power Generation Company Limited. The switching steps and the matters needing attention in the switching process were described, which are useful for safe and stable operation of the power units.
Key words: Key words:auxiliary power outage, interruption of power supply, auxiliary steam, switch over
李猛虎. 托电公司厂用电全失预案[J]. 华电技术, 2013, 35(10): 63-65.
LI Menghu. Precontrol plan for companywide auxiliary power outage of Togtoh Power Generation Company Limited[J]. Huadian Technology, 2013, 35(10): 63-65.
/ 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: https://www.hdpower.net/CN/
https://www.hdpower.net/CN/Y2013/V35/I10/63