首座国产化抽水蓄能电站投产期的创新管理

  

  1. (华电浙江龙游热电有限公司,浙江龙游〓324400)
  • 出版日期:2013-09-25 发布日期:2013-10-22

Innovative management of first domestic pumped storage power station during commissioning period

  1. (Huadian Zhejiang Longyou Thermal Power Company Limited, Longyou 324400, China)
  • Online:2013-09-25 Published:2013-10-22

摘要: 摘要:介绍了国网安徽响水涧抽水蓄能电站“为确保新设备顺利投运而开展的管理创新活动”的选题背景,分析了管理特征与创新点,论述了首座国产化抽水蓄能电站投产期创新管理的实施步骤,实施后实现了电站4台机组提前顺利投产,并使发电抽水启动成功率达到98%。

关键词: 关键词:抽蓄电站, 投产期, 管理特征, 创新点, 管理成果

Abstract: Abstract:The background of the topic “Innovative management action for ensuring new facilities can be put into operation successfully” in the Anhui Xiangshuijian Pumped Storage Power Station of State Grid was introduced. The management features and the innovation points were analyzed. The implementation steps of the innovative management of the first domestic pumped storage power station during commissioning period were expounded. After the innovative management was implemented, four units of the power station were put into operation successfully and ahead of time, and the startup success rate of the power generation units and the water pumps is 98%.

Key words: Key words:pumped storage power station, commissioning period, management feature, innovation point, management achievement