华电技术 ›› 2014, Vol. 36 ›› Issue (12): 26-28.

• 技术交流 • 上一篇    下一篇

1000MW机组施工机械配置分析

  

  1. (华电郑州机械设计研究院有限公司,郑州〓450015)
  • 出版日期:2014-12-25 发布日期:2015-02-04

Analysis on arrangement of construction machinery for 1000MW unit

  1. (Huadian Zhengzhou Mechanical Design Institute Company Limited, Zhengzhou 450015, China)
  • Online:2014-12-25 Published:2015-02-04

摘要: 摘要:介绍了国产1000MW锅炉的结构及吊装施工特点,给出了施工主力起重机的不同配置方案,结合施工案例对各配置方案进行了比较,在分析主力吊装设备发展趋势的基础上,提出新型动臂塔式起重机是火电各种炉型施工的首选。

关键词: 关键词:1000MW机组, 锅炉吊装, 动臂塔式起重机, 水平臂塔式起重机

Abstract: Abstract:The structure of domestic 1000MW unit boiler and the features of lifting construction of the boiler were introduced. The different arrangement schemes of the main construction cranes were given. Combining with project examples, the arrangement schemes were compared. Based on analysis of development trend of the main lifting equipment, it was proposed that the novel movable arm tower crane is the first choice for construction of various boilers in thermal power plants.

Key words: Keywords:1000MW unit, boiler lifting, movable arm tower crane, horizontal arm tower crane