华电技术 ›› 2014, Vol. 36 ›› Issue (7): 24-25.

• 技术交流 • 上一篇    下一篇

电厂运行过程中支吊架偏装量调整

  

  1. (1.浙江省火电建设公司,杭州〓310016;2.河南华电金源管道有限公司,郑州〓450051)
  • 出版日期:2014-07-25 发布日期:2014-09-23

Adjustment of installation offset value of supports in operation process of power plant

  1. (1.Zhejiang Thermal Power Construction Company, Hangzhou 310016, China; 2.Henan Huadian Jinyuan Pipeline Company Limited, Zhengzhou 450051, China)
  • Online:2014-07-25 Published:2014-09-23

摘要: 摘要:分析了某电厂运行过程中高压旁路减温水支吊架损坏的原因,通过安装有效的临时支吊架、重新设计安装新支吊架等措施,有效解决了运行过程中弹簧支吊架偏装量调整问题,供处理同类问题时参考。

关键词: 关键词:支吊架, 高压旁路, 偏装量调整, 减温水

Abstract: Abstract:The reasons of damage of high pressure bypass attemperating water supports in operation process of a power plant were analyzed. The effective temporary supports were installed, and then new supports were redesigned and installed. The problem of adjustment of installation offset value of the spring supports in operation process was solved effectively, which provides reference for handling with similar problems.

Key words: Keywords:support, high pressure bypass, adjustment of installation offset value, attemperating water