象鼻岭水电站地下厂房岩锚梁开挖质量控制

  

  1. (贵州西能电力建设有限公司,贵阳〓550004)
  • 出版日期:2015-03-25 发布日期:2015-05-14

Excavation quality control of rockanchored beam of underground powerhouse in Elephant Trunk Hill Hydropower Station

  1. (Guizhou Xineng Electric Power Construction Company Limited, Guiyang 550004, China)
  • Online:2015-03-25 Published:2015-05-14

摘要: 摘要:介绍了象鼻岭水电站地下厂房工程概况和地质特征,论述了地下厂房岩锚梁开挖质量控制措施,提出了岩锚梁开挖施工方案,通过爆破试验确定了合理参数,使开挖面残孔率、平整度和体型均满足规范和设计要求,联合验收质量达到了优良标准。

关键词: 关键词:鼻岭水电站, 地下厂房, 岩锚梁, 开挖质量控制

Abstract: Abstract:The general situation of the underground powerhouse project of Elephant Trunk Hill Hydropower Station and the geologic features were introduced. The quality control measures of the rockanchored beam excavation of the underground powerhouse were expounded. The construction scheme of the rockanchored beam excavation was put forward. According to the bursting test result, the rational parameters were determined. The remained halfhole rate, the flatness and the bodily form of the excavation surface meet the specification and design requirement. The conclusion of the united acceptance inspection is“excellent”.

Key words: Keywords:Elephant Trunk Hill Hydropower Station, underground powerhouse, rockanchored beam, excavation quality control