火电厂机组关停后厂用电系统改造思路与方案实例

  

  1. 华电淄博热电有限公司,山东淄博〓255054
  • 出版日期:2017-06-25 发布日期:2017-07-10

Service power system reconstruction plan and application practice after thermal power plant unit close down

  1. Huadian Zibo Heat and Power Company Limited, Zibo 255054, China
  • Online:2017-06-25 Published:2017-07-10

摘要:

随着国家节能减排工作的深入开展,对高能耗的小型火电机组实施关停将是必然趋势。华电淄博热电有限公司三期“上大压小”扩建工程(2×330MW)机组投产后,一期(2×71.5MW)机组将关停。由于一期与二期(2×145MW)机组在水、汽、煤、电系统均存在联系,且接带部分厂区内非生产用能,因此本文从安全、经济、平稳过渡等方面提出了一期机组关停后厂用电系统的改造思路和实际方案,并结合技术方案的具体实施过程总结出相关工程的管理方法和经验。

关键词:

Abstract:

With the development of energy saving and emission control, it is inevitable that small coalfired units be close down. After Huadian Zibo Heat and Power Company Limited third stage extension project (2×330MW) unit put into operation, the first stage was closed down. Due to the relevance of first and second stagey water, steam, coal and electricity system, this paper introduced a service power system reconstruction plan based on safety economy and smooth transition. Combined with specific implementation process,relevant project management method and experience was summarized.