华电技术 ›› 2009, Vol. 31 ›› Issue (10): 36-37.

• 研究与开发 • 上一篇    下一篇

FGD控制系统控制策略的优化与改进

孔庆甫   

  1. 杭州华电半山发电有限公司,浙江杭州 310015
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2009-10-25

Optimization and improvement of control strategy for FGD control system

KONG Qingfu   

  1. Hangzhou Huadian Banshan Power Generation Corporation Limited, Hangzhou 310015, China
  • Received:1900-01-01 Revised:1900-01-01 Published:2009-10-25

摘要: 介绍了杭州华电半山发电有限公司原FGD工艺流程及控制系统TXP存在的问题,将TXP改造为新型的NETWORK-6000系统,并在控制策略上进行改进、优化,改造效果良好。

关键词: 火电机组, 湿法脱硫, 控制系统, 策略改进

Abstract: The primary FGD process and the problems existed in TXP control system of Hangzhou Huadian Banshan Power Generation Corporation Limited were introduced. The TXP system had been replaced by novel NETWORK-6000 system, and the control strategy had been improved and optimized, and excellent effects of reformation were obtained.

Key words: thermal power unit, wet FGD, control system, improvement of strategy