燃煤电厂湿烟羽消除设计方案对比分析

  

  1. 中国华电科工集团有限公司,北京〓100160
  • 出版日期:2018-09-25 发布日期:2018-10-12

Comparative analysis of design schemes for wet plume removal in coalfired power plant

  1. China Huadian Engineering Company Limited, Beijing 100160, China
  • Online:2018-09-25 Published:2018-10-12

摘要:

湿法脱硫净烟气遇冷凝结析出水分,在烟囱出口形成湿烟羽,造成一定的视觉污染。通过分析湿烟羽生成和治理机理,探讨了环境温度和湿度对消除湿烟羽的影响。利用烟气加热、烟气降温、烟气降温再热等技术对某电厂的湿烟羽消除效果进行对比分析,得出冷却降温+间接换热+热二次风混合为最适应方案。此外,对某电厂的降温+再热方案进行分析,在净烟气管壳式换热分别下降3,5,7℃时,对比了不同材质和形式的降温换热器和再热换热器组合的经济回收期。 结论为消除湿烟羽的整体静态回收周期随着降温段温度的降低而缩短,宽通道板式冷凝换热器和宽通道板式再热器的组合最为经济。

关键词:

Abstract:

The moisture in flue gas after WFGD would be precipitated and form a wet plume at the chimney outlet, which causes certain visual pollution. By analyzing the mechanism and treatment of wet plume, the effects of ambient temperature and humidity on the elimination of wet plume are discussed. The effect of techniques on eliminating the wet plume of a power plant is compared and analyzed between flue gas heating, flue gas cooling, and flue gas cooling plus reheating. The technique which includes cooling, indirect heat exchange and hot secondary air mixing is the most suitable one. In addition, the cooling plus reheating scheme of a power plant is analyzed. When the temperature of flue gas shellandtube heat transfer decreases 3,5, and 7℃, the economic recovery period of the combination of cooling heat exchangers and reheat exchangers with different materials and various types are compared. The overall static recovery period of the wet plume elimination is shortened with the decrease of the temperature of cooling section, and the combination of the widechannel platetype condensing heat exchanger and the widechannel platetype reheater is the most economic.

Key words: