Huadian Technology ›› 2008, Vol. 30 ›› Issue (8): 24-26.

• 基础研究 • Previous Articles     Next Articles

The erection and commission of 1000MW domestic turbo-generator

ZHANG Xin-chun   

  1. Zouxian Power Plant, Huadian Power International Corporation Limited, Zoucheng 273522, China
  • Received:1900-01-01 Revised:1900-01-01 Published:2008-08-25

Abstract: The feature of the first domestic turbo-generator was described. The organization and management of turbo-generator erection and commission while the generator delivery was lagged seriously were expounded in detail. The feasibility of condenser covering while the generator is not in location was proofed, and the measures must be adopted were given too.

Key words: ultra-supercritical generation unit, 1000MW unit, construction plan, domestic participation