The problems occurred in commissioning of 660MW ultrasupercritical unit electric system and its countermeasures

WANG Shibo1,JING Xucheng1,XUE Fei2,YU Wentao1   

  1. 1.Anhui Huadian Wuhu Electric Power Corporation Limited,Wuhu 241300, China;2.Inner Mongolia Branch Office,Wind Power Generation Corporation Limited,China Guangdong Nuclear Power Group,Hohhot 010020, China
  • Received:1900-01-01 Revised:1900-01-01 Published:2009-03-25

Abstract: This paper roundly introduces the design of electric system and main equipments lectotype features of 2×660MW ultrasupercritical unit in Anhui Huadian Wuhu Electric Power Corporation Limited Firstterm Project,concurrently aiming at the merits & demerits of this design scenario and problems occurred in commissioning,several advices which should be noticed were proposed for the forthcoming design and working.

Key words: ultra-supercritical unit, electric system, design and equipments lectotype, problem analysis, resolvent