Huadian Technology ›› 2010, Vol. 32 ›› Issue (4): 45-47.
• 技术交流 • Previous Articles Next Articles
ZHANG Chunli
Received:
Revised:
Published:
Abstract: The faults occurred during installation and commission of DG490/13.73-Ⅱ2 CFB boiler manufactured by Dongfang Boiler Factory were discussed, which include the pulverized coal leakage of coal feeder system, the jam of limestone feeder, the coking of furnace and refeeder, distortion and burning loss of ignition duct expansion joint, air leakage of air heater and others. Some typical accident examples, such as the boiler shutdown due to severe water shortage caused by blocking fault of filter screen of feed pump and secondary consumption in tail duct caused by serious overtemperature in economizer area, were introduced, and the reasons of the accidents were analyzed. The solving method and concrete measures to prevent the accidents were proposed, which can be used as reference for same units in erection and operation.
Key words: circulating fluidized bed (CFB) boiler, economizer, secondary combustion, accident, measure
ZHANG Chunli. Analysis of faults in trial operation of DG490/13.73-Ⅱ2 CFB boiler[J]. Huadian Technology, 2010, 32(4): 45-47.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2010/V32/I4/45
Research on gas turbine combustion pressure fluctuation and the key technologies for its measurement
Necessity analysis of filtered containment venting system of nuclear reactor
Experimental study of dissolved oxygen’s effect on dissolved hydrogen analyzer of the main steam
Reasons analysis for tube blasting and preventive measures for superheater of 1000MW supercritical boiler
Application of mobile sonic soot blowers in economizer of 660MW boiler