Abstract: In a 300MW unit, after it was put into operation, the ash conveying system was not functioning properly, and the pipes often were plugged. The faults were analyzed, and according to the appeared problems, the pertinent improving measures were put forward. The result of the reformation was favorable.
Key words: ash conveying system, annular gap air flow, primary air flow, optimal reformation
JIN Yanhai. Optimal reformation of ash conveying system of 300MW unit[J]. Huadian Technology, 2010, 32(6): 52-54.