Huadian Technology ›› 2010, Vol. 32 ›› Issue (7): 26-30.
• 研究与开发 • Previous Articles Next Articles
TU Yiyuan
Received:
Revised:
Published:
Abstract: In March 24, 2009, during connection into the power grid of the Unit No.2 of Hunan Huadian Changsha Power Generation Limited, the connected generator was disconnected due to the incorrect tripping of the overexcitation protection. According to the record diagram of the protection fault recorder, the protection acting report and the tracking records of the whole connection operation process, the reasons of the protection incorrect tripping were analyzed; and the reasons of the endless loop of the sequential control logic were analyzed too. The problems existed in generator deeply underexcitation operation were discussed. Some relevant preventive measures were adopted in accordance with site practical situation.
Key words: unit connection into grid, generator over-excitation protection, protection incorrect tripping, reason analysis, preventive measure
TU Yiyuan. Analysis on the reasons of the false tripping of the generator overexcitation protection[J]. Huadian Technology, 2010, 32(7): 26-30.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2010/V32/I7/26
Reasons analysis for tube blasting and preventive measures for superheater of 1000MW supercritical boiler