Huadian Technology ›› 2010, Vol. 32 ›› Issue (7): 64-66.
• 技术交流 • Previous Articles Next Articles
ZHOU Bo,YE Hu
Received:
Revised:
Published:
Abstract: In the 2×300MW unit of the Guangdong Shaoguan Pingshi Power Plant (Plant B) extension project phase III, the problems existed in the initial installation of the cooling water system of the slag cooler for the circulating fluidized bed boiler were analyzed. Aiming at the problems occurred in operation, the cooling water system had been reformed for two times. The experiences of the reformation were summarized in this paper.
Key words: slag cooler, circulating fluidized bed boiler, cooling water system
ZHOU Bo;YE Hu. Analysis and reformation of cooling water system of Songling cylindrical slag cooler[J]. Huadian Technology, 2010, 32(7): 64-66.