Optimization of erection sequence of boiler steel frame

HAN Yunmai   

  1. Yunnan Huadian Kunming Power Generation Corporation Limited, Anning 650308,China
  • Received:1900-01-01 Revised:1900-01-01 Online:2010-07-26 Published:2010-07-26

Abstract: Based on the analysis of the conventional hoisting scheme for boiler drum combining with the physical condition, the hoisting sequence for #1 boiler steel frame and drum of Yunnan Huadian Kunming Power Generation Corporation Limited was optimized to reach the goal of reduction of erection time and enhancement of work efficiency.