Huadian Technology ›› 2012, Vol. 34 ›› Issue (8): 31-33.

• 技术交流 • Previous Articles     Next Articles

Experiment of primary frequency regulation of 2×600MW supercritical unit in Gongxian Power Plant

LAN Ligang1, GUO Tongshu2, ZHAO Ming2, ZHU Nengfei2   

  1. 1.Commissioning and Test Institute of Sichuan Electric Power Industry, Chengdu 610072, China; 2.Guodian Nanjing Automation Company Limited, Nanjing 210031, China
  • Received:1900-01-01 Revised:1900-01-01 Published:2012-08-25

Abstract:

The function setup of primary frequency regulation for the supercritical oncethrough boiler unit in Gongxian Power Plant was introduced.

Depending on the rational setup of the speed variation rate of DEH and CCS for primary frequency regulation, the fast action of DEH side in primary frequency

regulation operating process was realized; the primary frequency regulation requirement of the power grid was satisfied; and the frequency stabilization and

fine operation quality of the power grid were ensured.

Key words: once-through boiler, primary frequency regulation, digital electro-hydraulic control system (DEH), coordinated control system (CCS), experiment