Huadian Technology ›› 2013, Vol. 35 ›› Issue (10): 23-26.

Previous Articles     Next Articles

Black start measures of power units of Togtoh Power Generation Company Limited after all output transmission lines tripped

  

  1. (Inner Mongolia Datang International Togtoh Power Generation Company Limited, Togtoh 010206, China)
  • Online:2013-10-25 Published:2013-11-25

Abstract: Abstract:Due to the extreme rain and snow weather occurred at the winter of 2012, three of four 500kV output transmission lines of Togtoh Power Generation Company Limited tripped successively. Aiming at the probable accident of all four 500kV output lines tripping, the black start measures of units of Togtoh Power Generation Company Limited were proposed so as to ensure safety of the unit equipments.

Key words: Key words:output transmission line, trip, black start, equipment safety