Optimization of independent operation scheme of single power unit after output lines all tripped

  

  1. (Inner Mongolia Datang International Togtoh Power Generation Company Limited, Togtoh 010206, China)
  • Online:2013-10-25 Published:2013-11-25

Abstract: Abstract:After the 500kV output lines of Togtoh Power Generation Company Limited tripped successively, the power unit No.8 operated alone and provided the auxiliary power of whole plant. The operation condition was introduced. The treatment plan for independent operation of the unit No.8 was analyzed, the shortcomings of the plan were pointed out, and the plan was perfected.

Key words: Key words:transmission line tripping, output lines all tripped, operation of single power unit, scheme, optimization