Abstract:The national environment protection policy was introduced. The influence of canceling of FGD bypass on the unit was analyzed. The management improvement measures and the technical countermeasures after canceling of FDG bypass were expounded and verified by examples.
Key words: Key words:flue gas bypass, desulphurization, management improvement, technical measure
LI Yufeng, XU Shouyou. Technical analysis on canceling of FGD bypass of 600MW supercritical unit[J]. Huadian Technology, 2013, 35(7): 36-37.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2013/V35/I7/36
Experiment on energy saving optimization test of desulfurization and oxidation fans for 350MW units
Application and development of zeroemission treatment technology for desulphurization waste water from coalfired power plants
Research on reformation strategy of thermal power plant for “untra clean emissions”
Establishment of service power consumption rate model for desulphurization system of power plant based on SPSS
Integrated technology to treat poisoned slurry of limestonegypsum WFGD system