Abstract: Abstract:Taking the boiler No.1 of Guizhou Huadian Tangzhai Power Generation Company Limited as example, the main problems of scraper slag conveyer existing in process of 168h commissioning were analyzed. The problems needing emphatically attention at present were pointed out. Combining with the actual operation of the power plant, the feasible treatment measures were proposed.
Key words: Key words:scraper slag conveyer;tensioning wheel disjointed from chain;abrasion, treatment measure
LONG Weirong. Analysis on main problems existing in operation of scraper slag conveyer[J]. Huadian Technology, 2013, 35(8): 61-62.