Huadian Technology ›› 2014, Vol. 36 ›› Issue (1): 63-65.
Previous Articles Next Articles
Published:
Abstract: Abstract:The operation mode of 500kV system of a power plant was introduced. The configurations of the 500kV line protection and the 600MW unit protection were expounded. The process of the line switch maloperation accident and the reasons of the accident were analyzed, and the precontrol measures were put forward.
Key words: Keywords:switch trip without fault, selfignition of pulverized coal deposits on cable, reason analysis, precontrol measure
JIANG Anwei. Analysis on reasons of maloperation of 500kV line sweitch and precontrol measures[J]. Huadian Technology, 2014, 36(1): 63-65.