Abstract: Abstract:The original control technical scheme of emergency power supply system for Hubei Huadian Xisaishan Electricity Generating Corporation Limited were introduced , encountered problem during implementing process of the original scheme were discussed , reason that control function of emergency power supply system can not be put into use, and put forward new scheme for control of emergency power supply system were analyzed. After implementation of the new scheme, preferable result has been achieved.
Key words: Keywords:thermal power plant, alternating current emergency power supply, control technology
MA Hongtao. Control technology and application of emergency power supply[J]. Huadian Technology, 2014, 36(7): 52-54.