Huadian Technology ›› 2015, Vol. 37 ›› Issue (12): 52-54.

Previous Articles     Next Articles

Treatment measures of the malfunction of power plant isolated network

  

  1. Jiangsu Huadian Qishuyan Power Generation Company Limited,Changzhou 213011,China
  • Online:2015-12-25 Published:2016-02-02

Abstract:

Abstract:A certain power plant set up two 220kV power line tripped at the same time,and caused isolated network operation.After diagnosing the problem of 220kV power line,the system runs again by following the system recovery method,and the buses of 220kV and auxiliary power are bake to service as well,which allows paralleling operation and guarantees the safety of host equipment.

Key words: ">Keywords:">grid combination, trip, isolated network operation, electrical auxiliary system