Abstract:After analyzing Huadian Laizhou Power Plant Company Limited No.2 boiler water wall high temperature corrosion causes,the plan of to provide side wind on the both side of furnace to reduce and prevent reducing atmosphere and high temperature corrosion on side water wall was claimed.After reconstruction,cheek damper opening test was carried out.Based the test result,the advantaged and notes of reconstruction plan were summarized.
Key words: Keywords:low , NOx burner, water wall, high temperature corrosion, reducing atmosphere, side wind, hot primary air, load
WEI Daojun. Solution study of 1000MW boiler side water wall high temperature corrosion[J]. Huadian Technology, 2016, 38(2): 1-5.