A power plant’s 350MW boiler combustion test adjustment and anticoking test study

  

  1. Huazhong University of Science and Technology School of Energy and Power Engineering, Wuhan 430070, China
  • Published:2017-07-25

Abstract:

To solve the problem of boiler coking and NOxoveremission, a series of tests was carried out. The boiler operation status and cause of serious coking was accurately indicated. By improvement adjustment, boiler opertaion and NOxemission was optimized. Constant coking was solved. Boiler combustion adjustment and anticoking test achieved expectation.