Huadian Technology ›› 2018, Vol. 40 ›› Issue (10): 63-64.

Previous Articles     Next Articles

Technical practice of denitration system for 600MW coalfired unit before gridconnection

  

  1. Huaneng Tongchuan Zhaojin Power Plant, Tongchuan 727100, China
  • Published:2018-11-26

Abstract:

Before the technical reform on equipment in Huaneng Tongchuan Zhaojin Power Plant, indepth analysis of the parameters at each stage before startup process were carried out. By optimizing the operation, the flue gas temperature at inlet of denitration system before gridconnection increased from 265℃ to 298℃. The smoke temperature reached the minimum temperature required by continuous spraying ammonia of denitration catalyst. The denitration system was put into practice before the gridconnection. The main technical measures and parameters before and after the adjustment are introduced for reference in solving similar problems.