Huadian Technology ›› 2019, Vol. 41 ›› Issue (8): 24-26.

Previous Articles     Next Articles

Cause analysis and solution for ignition failure of V94.3A gas turbine

  

  1. State Power Investment Group Zhengzhou Gas Power Generation Company Limited, Zhengzhou 450001, China

  • Online:2019-08-26 Published:2019-09-06

Abstract:

There are frequent failures in startup and ignition process of a V94.3A gas turbine in a gasfired power plant. By analyzing its operating data, it is found out that high ambient humidity and poor draining effect of diffusion combustion natural gas pipelines will affect the the ignition of units.Effective drainage measures must be taken during the operation, before the shutdown and during the maintenance of the unit, which effectively improves the success rate of the unit ignition.