300MW机组投产初期的问题分析及优化运行

陈立志   

  1. 华电哈尔滨热电有限责任公司,黑龙江哈尔滨150046
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2011-03-25 发布日期:2011-03-25

Analysis on problems of 300MW unit occurred during early period of production and optimized operation

CHEN Lizhi   

  1. Huadian Harbin Thermal Power Corporation Limited, Harbin 150064, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2011-03-25 Published:2011-03-25

摘要: 对华电哈尔滨热电有限责任公司2台300MW火力发电供热机组在投产初期调试和运行方面出现的问题进行了分析。对机组的一些设备进行合理改造、对运行方式进行合理改变后,提高了机组的安全性和经济性。

关键词: 投产调试, 设备改造, 运行方式, 安全性, 经济性

Abstract: The problems of two 300MW thermal power generating and heat providing units of Huadian Harbin Thermal Power Corporation Limited occurred in commission and operation during early period of production were analyzed. Some devices of the units were reformed rationally, and the operation mode was improved reasonably, so the security and the economical efficiency of the units were raised. 

Key words: completion of starting-up and adjustment operation, equipment reformation, operation mode, security, economic efficiency