灰分选装置的投运及收益

黄献华   

  1. 华电新疆发电有限公司红雁池电厂,新疆乌鲁木齐830047
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2012-07-25 发布日期:2012-07-25

Commissioning of ash sorting device and benefit

HUANG Xianhua   

  1. Hongyanchi Power Plant of Huadian Xinjiang Power Generation Company Limited, Urumqi 830047, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2012-07-25 Published:2012-07-25

摘要: 对华电新疆发电有限公司红雁池电厂灰分选装置不能正常投运的情况进行了分析,对灰分选装置进行了调试,保证了系统的正常投入。将分选后的灰综合利用,取得了较好的经济效益。

关键词: 灰分选装置, 调试, 综合利用, 收益

Abstract: The ash sorting device put into operation improper in Hongyanchi Power Plant of Huadian Xinjiang Power Generation Company Limited was analyzed.The ash sorting device was debugged; and the system was put into operation normally. The better economical gains of multipurpose use of the sorted ash were obtained.

Key words: ash sorting device, debug, multipurpose use, gain