The Problems Existing in Commissioning of 1000MW Ultra-supercritical Unit and the Solutions

ZHANG Xin-chun   

  1. Huadian Power International Co., Ltd., Zouxian Power Plant,Zoucheng 273522,China
  • Received:1900-01-01 Revised:1900-01-01 Online:2008-05-25 Published:2008-05-25
  • Contact: ZHANG Xin-chun

Abstract: The features of the 1000MW ultra-supercritical unit of the phase Ⅳ project in Huadian International Zouxian power plant were introduced. The problems appeared during commissioning process and their solutions were discussed. Some matters needed to paying attention during total start-up period of ultra-supercritical turbine were summed up. It is expected that this article will be referable for construction and commission of the same type units by author.

Key words: 1000MW ultra-supercritical unit, trial operation, problem, solution