Huadian Technology ›› 2010, Vol. 32 ›› Issue (9): 44-48.
• 研究与开发 • Previous Articles Next Articles
WEI Shengluan
Received:
Revised:
Published:
Abstract: The vacuity of the 2×150MW unit of the Sichuan Huadian Panzhihua Sanwei Power Generation Corporation Limited was lower, and this caused the safety and the economical efficiency of the unit operation to be decreased. The problems existed in the manufacturing, the installation, the commissioning and the operation of the unit and the factors causing the vacuity of the unit decreasing were analyzed. The relevant countermeasures were put forward, so it is ensured that the unit operates safely and economically under rational back pressure.
Key words: condenser, vacuity, reason analysis, preventive measure
WEI Shengluan. Reason of vacuity decreasing of 150MW steam turbine unit and countermeasures[J]. Huadian Technology, 2010, 32(9): 44-48.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2010/V32/I9/44
Scale analysis and comprehensive treatment of condenser stainless steel tubes
Reasons analysis for tube blasting and preventive measures for superheater of 1000MW supercritical boiler