Huadian Technology ›› 2011, Vol. 33 ›› Issue (1): 21-26.

• 研究与开发 • Previous Articles     Next Articles

Analysis on network framework of Mark VI control system for gas turbine

MAO Huajun   

  1. Wangting Power Plant, Suzhou 215155, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2011-01-25 Published:2011-01-25

Abstract: The basic working principle of Mark VI turbine control system used in gassteam combined cycle generator unit was introduced. The applications of Ethernet, VLAN, the time synchronization and other technologies in the control system were analyzed. The related experiences were summarized.

Key words: Mark VI control system, topology, Ethernet, virtual local area network (VLAN)