Abstract: In Gongyi Yulian Power Plant, when the 300MW unit turbine was latched on again during its coasting operation after it was shutdown, the opening of the adjust gate was increased suddenly and rapidly; the rotate speed of the turbine was increased sharply; and the overspeed protection of the turbine was acted. The problems mentioned above were analyzed and treated, and favorable effect was obtained.
Key words: digital electro hydraulic control system (DEH), coasting operation after shutdown, PID adjuster, overspeed protection, fault analysis
LI Xingzhao;SONG Guofeng;CHEN Shuqin;HAI Guangxing. Analysis on fault of rotary speed control of 300MW unit steam turbine and treatment measures[J]. Huadian Technology, 2011, 33(9): 50-52.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2011/V33/I9/50
Fault analysis on desulfurization DCS signal interference in a thermal power plant
Analysis on faults of multipumps concentrated phase pneumatic ash removal system