Abstract: The first leakage of highpressure heater No.2 of unit No.1 in Guangdong Yudean Jinghai Power Generation Company Limited was introduced. The reasons of the leakage fault were analyzed. The relevant preventive measures were formulated, and the matters needing attention in the fault treating process were pointed out. The results of this paper provide certain reference for operation and maintenance of highpressure heaters of power plants.
Key words: 600MW unit, high-pressure heater, leakage, maintenance, preventive measure
GUAN Jirong. Reason analysis and preventive measures of highpressure heater leakage of 600MW unit[J]. Huadian Technology, 2012, 34(6): 11-12.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2012/V34/I6/11
Comparative analysis of calculation models for thermal efficiencies of waste heat boilers in gassteam combined cycle units
Optimization of air preheater leakage control system in 670MW unit
Comparison of DLN1.0+ and LEC-NextGen combustion system
Reasons analysis for tube blasting and preventive measures for superheater of 1000MW supercritical boiler
Predictive maintenance of power plant equipment driven by “cloud+client” big data