Huadian Technology ›› 2014, Vol. 36 ›› Issue (11): 43-45.
Previous Articles Next Articles
Published:
Abstract: Abstract:In an 110kV substation, when the 110kV line failed and relevant beaker tripped, the automatic bus transfer equipments of the substation did not act, and related transformer and 110kV bus were cutout. Using the theoretical analysis and logic verification method, the accident was analyzed and discussed. The preventive measures in operation and maintenance were pointed out. The results in this paper provide reference for design and operation of the automatic bus transfer equipments.
Key words: Keywords:automatic bus transfer equipment, rejecting act;technical measure
CHEN Hangsheng, ZHANG Guoping, CHEN Ping. Analysis on rejecting act accident of automatic bus transfer equipments in an 110kV substation and treatment measures[J]. Huadian Technology, 2014, 36(11): 43-45.