Abstract:

Abstract:A power plant’s drain system was blocked while low load operation. After analyzing operating data and equipment installation, which was known, in low load condition, low pressure difference is not able to overcome the resistance of equipment and level difference. The authors indicated the improvement measurements that to provide additional draining pump. The authors also provided and compared two improvement plan.