Huadian Technology ›› 2017, Vol. 39 ›› Issue (6): 59-60.

Previous Articles     Next Articles

600MW supercritical W flame boiler water pressure test system improvement

  

  1. Guizhou Huadian Tongzi Power Plant Company Limited,Zunyi 563200, China
  • Published:2017-06-25

Abstract:

The practice that use air preheater high pressure wash pump as boiler primary system hydraulic test boost pump was introduced. The water source, pipeline and control system was improved. The improvement of existed boiler primary system hydraulic test system was realized. The problems of long time consumption, complicated operation, high tests cost and maintenance delay was avoided.

Key words: