Huadian Technology ›› 2012, Vol. 34 ›› Issue (S1): 72-74.

• 技术经济 • Previous Articles     Next Articles

Analysis on optimization of human resource management for distributed energy power stations

ZHANG Yaohua   

  1. Shanghai Huadian Minhang Energy Company Limited, Shanghai 201108, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2012-11-10 Published:2012-11-10

Abstract: The basic state of Shanghai Huadian Xinzhuang Distributed Energy Power Station was introduced based on the gas turbine LM6000. The purpose of the optimization of human resource management was expounded. The basic employment mode of distributed energy power station was analyzed. The concrete measures for optimization of human resource management were put forward.

Key words: distributed energy power station, gas turbine, human resource management, management optimization, measure