Huadian Technology ›› 2010, Vol. 32 ›› Issue (2): 46-50.
• 技术交流 • Previous Articles Next Articles
XIAO Changge, HU Shanyun, YANG Yuhong
Received:
Revised:
Online:
Published:
Abstract: The control level of auxiliary shops of largescale thermal power unit and various monitoring scheme were discoursed, and the problems existing in auxiliary shop centralized monitoring network system were discussed. Several key technologies restricting the auxiliary shop monitoring network system were analyzed in detail. Combining with Guodian Feixian Power Plant phase I project (2×600MW supercritical units), the monitoring plan and configuration scheme of auxiliary shop centralized monitoring network system of largescale thermal power unit based on industrial Ethernet were provided.
Key words: centralized monitor and control, control mode, industrial Ethernet, auxiliary control network, configuration
XIAO Changge;HU Shanyun;YANG Yuhong. Centralized monitoring network scheme and configuration for auxiliary shop of largescale thermal power unit[J]. Huadian Technology, 2010, 32(2): 46-50.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.hdpower.net/EN/
https://www.hdpower.net/EN/Y2010/V32/I2/46
Feasibility research on redundancy removal and derating of coal handling systems in large and medium coalfired power plants
Design and application of intelligent auxiliary debugging system for largescale energy storage power station