Improvement of protection of 9E gas turbine Mark V control system by double configuration

LI Honglian,WANG Huanhuan   

  1. Shanghai Fengxian Gas Turbine Power Generation Company Limited, Shanghai 201403, China
  • Received:1900-01-01 Revised:1900-01-01 Online:2012-11-10 Published:2012-11-10

Abstract: The nonredundant protection items in the Mark V control system of the PG9171E gas turbine were analyzed. A concrete improvement scheme was proposed, and the double configuration of the protection items was realized. The operation stability of the whole unit was improved. The result of this paper can be used as reference for similar units in protection improvement by double configuration.

Key words: gas turbine, Mark V control system, double configured protection, non-redundant protection, improvement