Huadian Technology ›› 2013, Vol. 35 ›› Issue (12): 54-56.

Previous Articles     Next Articles

Resistance measurement of breaker loop of HGIS

  

  1. (1.Maintenance Company of Henan Electric Power Company, Anyang 455000, China; 2.Anyang Iron & Steel Corporation Limited, Anyang 455000, China)
  • Online:2013-12-25 Published:2014-02-19

Abstract:

Abstract:In recent years, along with enlargement of the power grid scale, many EHV substations were built. Due to the pressures of environment protection and land occupation, a large quantity of gas insulated metalenclosed switchgear (GIS) was widely used in substation construction. The GIS is becoming indispensable equipment for substations. A mistake, which easily occurs in resistance measurement of breaker conducting loop of the hybrid gas insulated switchgear (HGIS), was analyzed, and some correct measurement methods and the matters needing attention in the measurement were summarized. The result in this paper can be used as reference for handling with similar problems.

Key words: Key words:gas insulated metalenclosed switchgear, breaker, loop, resistance measurement, temperature