摘要: 介绍了某电厂600MW级发电机组新型厂用电系统的优化设计方案,对设计方案进行了分析比较,最终选出了适合于该电厂实际情况的方案。 

关键词: 发电厂, 600MW级机组, 厂用电系统, 优化, 设计

Abstract: The optimized design of novel station auxiliary power system for the 600MW unit of a power plant was introduced. Design schemes have been analyzed and compared ,and the scheme suitable for the practical situation of the power plant had been selected finally.

Key words: power plant, 600MW level unit, station auxiliary power system, optimization, design